See More Vessel Transfer and Launch

In 2007, HEGER designed an elevated track to be placed on the pontoon deck of VIGOR’s Floating Dock No. 5 in Portland, OR, using existing steel towers. The track is used for transfer and launch of newly constructed vessels from shore and for transfer of vessels undergoing long term repair to shore. HEGER analyzed the existing floating dock structure’s capability to support the transfer loads. We developed a pumping plan for use during the transfer.

Elevated Track on Pontoon Deck - Vessel Transfer System for Existing AFDB Floating Dock
Figure 1 – Elevated Track on Pontoon Deck
Transfer of 2,500 Ton LCS-2 Class Vessel
12,000 Ton Capacity Transfer System for Existing Floating Dock